1) Remove all things that do not need in the pump.
(2) Check if the unit and auxiliary equipment operate normally.
(3) Electrical equipment has been installed and has been tested, debugged, conforming to the requirements of the operation.
(4) Carry out motor idling test and check if rotate direction of the motor is correct.
(5) Check if the valve is flexible and reliable.
(6) Check if the ground wire is in good condition.